PLM, BOM & Digital Thread calculator
Manufacturing BOM Conversion Load Calculator
Find how long restructuring an engineering bill of materials into a manufacturing one will take. You need the line items, the conversion rate, the allowance and the planner hours scheduled.
What this calculator does
- Planner hours converting an engineering BOM into a manufacturing BOM needs, with review and rework time, against the hours scheduled.
Formula used
- Base conversion hours = EBOM line items to convert ÷ line items converted per hour
- Required conversion hours = base conversion hours × (1 + allowance ÷ 100)
- Scheduled hours left = planner hours scheduled − required hours; load (%) = required ÷ scheduled × 100
Inputs explained
- EBOM Line Items to Convert: Engineering BOM lines to restructure into the manufacturing BOM.
- Line Items Converted per Hour: Lines one planner converts per hour, from the log.
- Setup, Review and Rework Allowance: Extra time for setup, review with engineering and rework.
- Planner Hours Scheduled: Hours scheduled for the conversion.
How to use the result
- Best suited to planning the manufacturing BOM for a launch, sizing planners for a product transfer.
- Does not model new routings. Ignores lines blocked on unreleased parts.
Common questions
- What changes between an EBOM and an MBOM? Structure. The engineering BOM groups parts by function; the manufacturing BOM groups them by how and where they are built, adding consumables and phantoms.
- How do I set the conversion rate? Divide lines converted by planner hours on a past product. The 25 per hour default is an example only.
- What goes into the allowance? Setting up the structure, reviewing questions with engineering and reworking lines after the first build.
- What if the required hours exceed the schedule? The calculator warns and shows the overrun. Map standard lines with a rule, add a planner or stage the conversion by assembly.